The project was advertised for bid in April 2025 and bids were opened on May 13, 2025. A contract with the low bidder (Active Construction, Inc.) is scheduled for award on June 4, 2025 for the amount of $1,969,969. The City obtained funding via a Department of Ecology grant to complete final design and construction of the project.
Scope/Purpose
In the City’s continuing effort to improve water quality for Kitsap Lake, this project will provide treatment at four outfall locations that are currently untreated. The treatment will consist of installation of TAPE GULD approved systems above the outfalls in the roadway adjacent to each site. Treatment will be for suspended solids (TSS), dissolved copper, dissolved zinc, and total phosphorus.
Schedule
Ecology grant award for final design and construction awarded – March 6, 2024
Final design completed – April 2025
Advertised for construction – April 22, 2025
Bids opened May 13, 2025
Contract awarded June 4, 2025
Construction start – August 2025
Construction complete – December 2025
Funding
The project will be completed using the Department of Ecology grant. The grant will pay for 85% of the total cost to complete the design and construction. The Stormwater Utility will match the grant for the remaining 15% needed.
Contact Us
David Dinkuhn, PE Project Manager Ph: 360-473-3518 Email