Kitsap Way Culvert Replacement

CURRENT PROJECT STATUS UPDATE (December 7, 2021)

The project is getting close to completion with the remaining work items being road striping, a final clean up, and removing all of the traffic drums and other temporary traffic control. The striping work is weather dependent and can only be done with a fully dry road surface.

Traffic Impacts: Roadway is fully open. With the road striping, traffic will be shifted around for the time it takes to get markings down.  This work should be completed in less than one day.

IMG_2583November 24, 2021 – Installation of landscaping on north side of roadway.

SCOPE

The culvert under Kitsap Way was installed in 1927 and carries Ostrich Bay Creek. It is in poor shape after almost a century of use, undersized, and a fish barrier. This project replaces this problematic culvert with a new larger culvert that will be fish passable.

SCHEDULE

  • Design Started - December 2018
  • Permits approved – October 2020
  • Contract Award and Order Culvert – February/March 2021
  • Construction Started – August 2021
  • Construction Complete – November 2021

FUNDINGKitsapWayCulvertReplacement_map

Funding is by a loan from the Public Works Trust Board and includes replacement of the culvert on Kitsap Way, along with the culverts on Brentwood Drive and Price Road. For more information on the this project visit the Price Road and Brentwood Drive Culvert Replacements project webpage.

Total loan amount is $4,687,968

Construction cost for Kitsap Way is estimated to be $1.9 million
Construction cost for Brentwood and Price is estimated to be $2.3 million
Total design cost for all three culvert replacements is $489,988

ADDITIONAL DOCUMENTS

CONTACT US

  1. Gunnar Fridriksson
    Project Manager
    Ph: 360-473-5758
    Email