IMPORTANT NOTIFICATION OF UPCOMING PAVING
The City’s contractor Pape & Sons has scheduled overlay of the road during the week of November 1, weather pending. There will be significant disruption to traffic that residents should be aware of and residents should expect delays of up to 10 minutes while paving is completed.
Project Status and Schedule (October 27, 2021)
The water main has been installed and placed on-line in entirety. The City is restoring the road and intending to overlay the road in November, weather pending.
Project Overview
The project scope includes the installation of approximately 5,800 linear feet of ductile iron water main along Marine Drive and at Rocky Point Road NW intersection. The existing water main was installed in the 1930s and is both undersized and has reached the end of its useful life. The new watermain will provide improved fire flow and service to the residents along Marine Drive. Marine Dr. will receive a full road overlay.
The Design contract was awarded to KPG for $203,500 with engineering design completed on May 20, 2021 and the project construction contract was awarded by Bremerton City Council on July 7, 2021 to Pape & Sons in the amount of #2,018,002.35.