Marine Drive Water Main Replacement

Project Status and Schedule


The Design contract was awarded to KPG for $203,500. They will start design in December 2020 and construction is anticipated to begin in summer 2021.     

Project Overview


The project scope includes the installation of approximately 5,200 linear feet of 8-inch ductile iron water main along Marine Drive and Rocky Point Road Drive. The existing water main was installed in the 1940s and is both undersized and has reached the end of its useful life. The new watermain will provide improved fire flow and service to the residents along Marine Drive.

Related Documents