Price Rd and Brentwood Dr Culvert Replacements

CURRENT PROJECT STATUS UPDATE (October 18, 2022)

The Contractor has completed most of the work on Price Road with paving scheduled tentatively next week, depending on weather. Once paving is complete, work will fall to landscaping and installing guardrail. With guardrail in place, the road will be reopened. 

At Brentwood Drive, the Contractor will be placing the girders for the south half of the bridge this coming Tuesday. Work will then concentrate on the traffic barrier and then getting the new bridge ready for paving.

Traffic Impacts: 

  • Price Road - closure in place with detours. 
  • Brentwood Drive - expect delays with one-lane alternating traffic and intermittent closures.  NOTE:  Expect delays this coming Tuesday the 25th for installation of the girders for the south half of the bridge.

PriceRoadOctober 17, 2022 – Contractor installing waterproof membrane on Price Road bridge.

SCOPE

Both of the existing culverts for the two roadways are rated as blocking fish passage by WDFW, along with the culvert on Price Road being undersized. This culvert failed in 2005 causing the existing culvert and roadway being washed out. Both culverts are to be replaced with bridges, Price Road being a 43-foot bridge and Brentwood Drive being a 60-foot bridge.

Removal of these last two culverts on Ostrich Bay Creek will complete the removal of all City owned culverts/fish barriers from the creek.

PROPOSED SCHEDULEPriceBrentwoodCulvertReplacement_map

  • Design Started - December 2018
  • Design and Permitting Completed – Winter 2022
  • Contract Award and Order Girders – Spring 2022
  • Construction Started – June 2022
  • Construction Complete – December 2022

FUNDING

Funding is by a loan from the Public Works Trust Board and includes replacement of the culverts on Brentwood Drive and Price Road, along with the culvert on Kitsap Way. For more information on the Kitsap Way Culvert, visit the project webpage.

Total loan amount is $4,687,968

Construction cost for Brentwood and Price is estimated to be $2.3 million
Construction cost for Kitsap Way is estimated to be $1.9 million
Total design cost for all three culvert replacements is $489,988

ADDITIONAL INFORMATION

CONTACT US

  1. Gunnar Fridriksson
    Project Manager
    Ph: 360-473-5758
    Email