Project Overview

The City of Bremerton (City) plans to replace an existing steel 24” water transmission main starting at the outlet of Reservoir 4 along Sound Ridge Drive to the north end of the car dealerships along Oyster Bay Avenue N. The new pipe will be ductile iron.  The old pipe is 75 years old and has reached it’s useful life expectancy.  

The design consultant is RH2 Engineering of Tacoma, WA.


The overall budget for this project is $2,400,000, including design, construction, etc.


It is the goal Of the City to begin construction by the end of April 2018, finishing by the end of September 2018.  

Bidding for construction of this project is anticipated in March 2018. Design for this project is at 95% as of 1/19/18.