Oyster Bay Ave N 24-in Transmission Main

Project Status (Updated May 29, 2018)


The Project Bid Opening was held on March 29, 2018. The lowest responsive, responsible bidder is Nova Contracting with a bid in the amount of $1,084,124.90. The contractor mobilized on site and began the work on May 7, 2018 and Substantial Completion is expected by September 4, however, the project could be complete as early as the first part of August.

Main Line Construction began May 21st and is scheduled to be complete the end of June. After the 4th of July holiday, the Connections Phase of the project will begin. Connections will be made on Sound Ridge Dr., Auto Center, H St., Cottman Ave., Jones St West, and Autoplex Blvd.

Project Overview


The City of Bremerton (City) plans to replace an existing steel 24” water transmission main starting at the outlet of Reservoir 4 along Sound Ridge Drive to the north end of the car dealerships along Oyster Bay Avenue N. The new pipe will be ductile iron.  The old pipe is 75 years old and has reached it’s useful life expectancy.  

The design consultant is RH2 Engineering of Tacoma, WA.

Budget


The overall budget for this project is $2,400,000, including design, construction, etc.

Schedule


It is the goal Of the City to begin construction by the end of April 2018, finishing by the end of September 2018.  

Bidding for construction of this project is anticipated in March 2018. Design for this project is at 95% as of 1/19/18.

Site Plan - OB 24-inch Transmission Main