The work to be completed includes rehabilitating approximately 6,500 lineal feet of sanitary sewer and 1,600 lineal feet of storm sewer using the cure-in-place-pipe (CIPP) method. This project also includes cleaning and video inspection of approximately 5,400 lineal feet of sanitary sewer pipe. The CIPP lining extends the life of sewer and storm drain lines by about 50 years at a fraction of the cost of replacing these pipelines.
Project Status (July 2025)
Project was awarded to Insituform Technologies, LLC. Pipe cleaning and inspection work was completed in July, with lining scheduled to begin in mid-August.
Project Sites
See the City's 2025 Construction Map (PDF) for locations (*some locations have been removed from project scope since published date of construction map).
Funding
Contract Amount: $771,557.97
Schedule
Construction began in June 2025. Anticipated completion is in September 2025.