Project Status and Schedule


The Design contract was awarded to KPG for $203,500. Engineering design will be completed on May 7, 2021 and project contract shall be awarded by Bremerton City Council on June 16, 2021. Construction is estimated to begin on July 6, 2021 with project paving to be completed by October 15, 2021 and total project to be concluded by October 31, 2021    

Project Overview


The project scope includes the installation of approximately 5,600 linear feet of ductile iron water main along Marine Drive and  at Rocky Point Road NW intersection. The existing water main was installed in the 1930s and is both undersized and has reached the end of its useful life. The new watermain will provide improved fire flow and service to the residents along Marine Drive. Marine Dr. will receive a full road grind and inlay and driveway approach will be paved.